Saturday, May 19, 2012
image image image image image image image image image image image image image image image image image image image image image image image image image image image image image image
Second section of an arch being installed. February 2012.
Strandherd-Armstrong Bridge construction continues. Looking east at north bridge launching truss sitting on temporary piers. February 2012.
North side of supported permanent bridge deck floor beams (white sections.) February 2012.
Arch sections stored on site awaiting welding together and suspension from support towers. February 2012.
Looking east between north and centre bridge launching trusses sitting on temporary piers. February 2012.
The first top piece of Arch from the North Arch being put in place on top of tower. February 2012.
Looking West at River and Temporary Piers; Note West abutment in Background. January 2012.
Placing Deck Formwork. January 2012.
Assembling Floor Beams. January 2012.
Lifting Arch Segment onto Welding Frame On-site. January 2012.
Launching North Temporary Truss across Rideau River. January 2012.
Assembling Temporary Launching Trusses on West Approach. January 2012.
Looking South at Completed Steel Deck and Temporary Arch Towers on East Approach. January 2012
Bridge starting to take shape, December 2011. View from Prince of Wales at Strandherd Dr.
The future Strandherd Armstrong Bridge begins to take shape along the Rideau River
Looking north from the centre temporary pier on the west shore (September 2011)
Erecting shoring for floorbeam assembly - east approach (September 2011)
Delivery of crane for deck and arch steel assembly (September 2011)
Looking west across the river (August 2011)
West abutment thrust blocks, three arch anchors on inclined face (August 2011)
River view of completed west foundations with temporary piers on right (August 2011)
Assembly of launching rails, east approach (August 2011)
Stay-cable anchors delivered to site (August 2011)
Arch fabrication (August 2011)
Launching the rail bed - facing Earl Armstong Road (July 2011)
Launching the rail bed (July 2011)
Backfilling west abutment wall (July 2011)
Casting northwest concrete thrust block (June 2011)
Arch fabrication in progress - looking inside of arch on its side (June 2011)
Completed Painted Floorbeams waiting to be shipped to bridge site (June 2011)
Thursday, 22 July 2010 13:00

High tech bridge project underway

Last Updated: July 21, 2010 6:13pm

It’s not often in Ottawa that bridge construction draws a crowd, but the city is already predicting a spectacle when a new overpass slides into place across the Rideau River.

dynamic_resize.jpgThe $50-million Strandherd-Armstrong bridge, which will span the river at Earl Armstrong Rd., has a completion date of early 2012 and work has already started. The city recently awarded the building contract to ConCreate USL, headquartered in Bolton, Ont.

It will be the first bridge built across the Rideau River in Ottawa since the Hunt Club Rd. bridge was constructed in 1986.

In the case of the Strandherd-Armstrong bridge, construction won’t happen across the river. Instead, workers will built the bridge at a staging area and use a track system to slide it into place between River Rd. and Prince of Wales Dr.

The bridge will be constructed on tracks on the east side. At the same time workers are assembling the bridge, others will build a trestle system across the river so they can eventually push the bridge into place.

“This is going to be an impressive engineering feat,” Gloucester-South Nepean Steve Desroches said.

bridge_under_construction3.jpg

Desroches, who represents the area, said he has been receiving calls from residents already wanting information on where they can watch the bridge being built. The calls have prompted City Hall to start thinking about how they can accommodate spectators when the bridge is slid into place.

That could happen in fall 2011, but there are no time restrictions.

The last time a bridge commanded an audience in Ottawa was in 2007 when the province replaced the Island Park Dr. bridge at Hwy. 417. The replacement happened overnight after workers built the bridge in a staging area.

Hundreds of people filled bleacher seating to watch the climactic moment of the bridge construction.

Rolling the Strandherd-Armstrong bridge across the river could bring back that excitement.

“I expect there will be the same level of interest,” Desroches said.

There are several advantages to building the bridge on land rather than over the river.

Marcel Delph, the city’s manager of the project, said environmental impacts are minimized and worker safety is enhanced.

“We will be casting the concrete deck in the bridge’s final location because it weighs more and jacking the steel superstructure would be very heavy,” Delph said.

The bridge will weigh about 8,000 metric tonnes when it’s slid into place.

Delph said this construction plan is unique for such a large bridge.

This e-mail address is being protected from spambots. You need JavaScript enabled to view it

kbhc
 

sab

 

fb
Follow Steve on Facebook
 

alt

OCTranspo 485 Small

sab

ottawa small

Wardmap side

sab

sab

 

Serving the Communities of Barrhaven, Riverside South and Findlay Creek

Login Form