Saturday, May 19, 2012
image image image image image image image image image image image image image image image image image image image image image image image image image image image image image image
Second section of an arch being installed. February 2012.
Strandherd-Armstrong Bridge construction continues. Looking east at north bridge launching truss sitting on temporary piers. February 2012.
North side of supported permanent bridge deck floor beams (white sections.) February 2012.
Arch sections stored on site awaiting welding together and suspension from support towers. February 2012.
Looking east between north and centre bridge launching trusses sitting on temporary piers. February 2012.
The first top piece of Arch from the North Arch being put in place on top of tower. February 2012.
Looking West at River and Temporary Piers; Note West abutment in Background. January 2012.
Placing Deck Formwork. January 2012.
Assembling Floor Beams. January 2012.
Lifting Arch Segment onto Welding Frame On-site. January 2012.
Launching North Temporary Truss across Rideau River. January 2012.
Assembling Temporary Launching Trusses on West Approach. January 2012.
Looking South at Completed Steel Deck and Temporary Arch Towers on East Approach. January 2012
Bridge starting to take shape, December 2011. View from Prince of Wales at Strandherd Dr.
The future Strandherd Armstrong Bridge begins to take shape along the Rideau River
Looking north from the centre temporary pier on the west shore (September 2011)
Erecting shoring for floorbeam assembly - east approach (September 2011)
Delivery of crane for deck and arch steel assembly (September 2011)
Looking west across the river (August 2011)
West abutment thrust blocks, three arch anchors on inclined face (August 2011)
River view of completed west foundations with temporary piers on right (August 2011)
Assembly of launching rails, east approach (August 2011)
Stay-cable anchors delivered to site (August 2011)
Arch fabrication (August 2011)
Launching the rail bed - facing Earl Armstong Road (July 2011)
Launching the rail bed (July 2011)
Backfilling west abutment wall (July 2011)
Casting northwest concrete thrust block (June 2011)
Arch fabrication in progress - looking inside of arch on its side (June 2011)
Completed Painted Floorbeams waiting to be shipped to bridge site (June 2011)
Friday, 18 June 2010 16:21

Strandherd Armstrong Bridge Update - June 18, 2010

 

This past Monday, June 14th, I had the opportunity to speak with city officials and senior engineers at ConCreate USL, the contractor awarded the tender for the construction of the Strandherd-Armstrong Bridge, regarding the upcoming construction.

During our conversation with the contractor, I had the opportunity to underline the importance of the project and the need to deliver the project on time and on budget. I was also pleased to hear that Cherubini Group of Companies of Dartmouth, Halifax, is assembling the steel components of the bridge.   It is good to know that the economic benefits of the bridge will remain on Canadian soil.  

I have the utmost faith in these two companies to build us a beautiful, long-standing connection between Riverside South and Barrhaven. Both companies have impressive portfolios and will each bring their expertise to the construction of the bridge.

I look forward to seeing them get on their way with construction over the coming summer months. The bridge is anticipated to open in 2012.

kbhc
 

sab

 

fb
Follow Steve on Facebook
 

alt

OCTranspo 485 Small

sab

ottawa small

Wardmap side

sab

sab

 

Serving the Communities of Barrhaven, Riverside South and Findlay Creek

Login Form