Saturday, May 19, 2012
image image image image image image image image image image image image image image image image image image image image image image image image image image image image image image
Second section of an arch being installed. February 2012.
Strandherd-Armstrong Bridge construction continues. Looking east at north bridge launching truss sitting on temporary piers. February 2012.
North side of supported permanent bridge deck floor beams (white sections.) February 2012.
Arch sections stored on site awaiting welding together and suspension from support towers. February 2012.
Looking east between north and centre bridge launching trusses sitting on temporary piers. February 2012.
The first top piece of Arch from the North Arch being put in place on top of tower. February 2012.
Looking West at River and Temporary Piers; Note West abutment in Background. January 2012.
Placing Deck Formwork. January 2012.
Assembling Floor Beams. January 2012.
Lifting Arch Segment onto Welding Frame On-site. January 2012.
Launching North Temporary Truss across Rideau River. January 2012.
Assembling Temporary Launching Trusses on West Approach. January 2012.
Looking South at Completed Steel Deck and Temporary Arch Towers on East Approach. January 2012
Bridge starting to take shape, December 2011. View from Prince of Wales at Strandherd Dr.
The future Strandherd Armstrong Bridge begins to take shape along the Rideau River
Looking north from the centre temporary pier on the west shore (September 2011)
Erecting shoring for floorbeam assembly - east approach (September 2011)
Delivery of crane for deck and arch steel assembly (September 2011)
Looking west across the river (August 2011)
West abutment thrust blocks, three arch anchors on inclined face (August 2011)
River view of completed west foundations with temporary piers on right (August 2011)
Assembly of launching rails, east approach (August 2011)
Stay-cable anchors delivered to site (August 2011)
Arch fabrication (August 2011)
Launching the rail bed - facing Earl Armstong Road (July 2011)
Launching the rail bed (July 2011)
Backfilling west abutment wall (July 2011)
Casting northwest concrete thrust block (June 2011)
Arch fabrication in progress - looking inside of arch on its side (June 2011)
Completed Painted Floorbeams waiting to be shipped to bridge site (June 2011)
Friday, 22 April 2011 16:28

Strandherd-Armstrong Bridge’s Western Footing

Strandherd-Armstrong Bridge’s Western Footing

I would like to update residents on the continued progress of the Strandherd-Armstrong Bridge.

On Thursday, April 14, 2011, the City of Ottawa’s contractor for the Strandherd-Armstrong Bridge poured approximately 1400 cubic metres of concrete to form the western footing of the $48 million city bridge spanning the Rideau River. The work to cast the west footing of the bridge, entailed casting a large quantity of concrete in a continuous pour. This work involved the hauling, pumping and placement of concrete and required overnight activity to get the continuous pour completed. The cumulative load weighed approximately 3000 tonnes.

I am pleased to see the bridge continue to take its shape. We will begin to see more prominent development of the bridge over the coming months. I know this project is a priority for residents and I am pleased to see progress being made.

 

 

kbhc
 

sab

 

fb
Follow Steve on Facebook
 

alt

OCTranspo 485 Small

sab

ottawa small

Wardmap side

sab

sab

 

Serving the Communities of Barrhaven, Riverside South and Findlay Creek

Login Form