Monday, March 10, 2014
image image image image image image image image image image image image image image image image image image image image image image image image image image image image image image
Strandherd-Armstrong Bridge Construction - May 2013
Strandherd-Armstrong Bridge Construction - May 2013
Strandherd-Armstrong Bridge Construction - May 2013
Strandherd-Armstrong Bridge Construction - April 2013
Strandherd-Armstrong Bridge Construction - April 2013
Strandherd-Armstrong Bridge Construction - April 2013
Strandherd-Armstrong Bridge Construction - April 2013
Strandherd-Armstrong Bridge Construction - April 2013
Strandherd-Armstrong Bridge Construction - April 2013
The third arch begins to take shape - February 2013
Night-time view - December 2012
Night-time view - December 2012
Night-time view - December 2012
Night-time view - December 2012
Two of the arches taking shape - November 2012
View from the water, facing East - September 2012
The view across the Rideau River from the top of the arches. August 2012.
More arch segments arriving from Nova Scotia. August 2012.
Arch segments arriving from Nova Scotia. July 2012.
Bridge's arch beginning to take shape. March 2012.
Arch pieces ready to be welded in place. March 2012.
Second section of an arch being installed. February 2012.
Strandherd-Armstrong Bridge construction continues. Looking east at north bridge launching truss sitting on temporary piers. February 2012.
North side of supported permanent bridge deck floor beams (white sections.) February 2012.
Arch sections stored on site awaiting welding together and suspension from support towers. February 2012.
Looking east between north and centre bridge launching trusses sitting on temporary piers. February 2012.
The first top piece of Arch from the North Arch being put in place on top of tower. February 2012.
Looking West at River and Temporary Piers; Note West abutment in Background. January 2012.
Placing Deck Formwork. January 2012.
Assembling Floor Beams. January 2012.
 
 
Monday, 03 March 2014 09:52

Strandherd-Armstrong Bridge Update – March 2014

Strandherd-Armstrong Bridge Update – March 2014

I would like to provide residents with an update on the construction of the Strandherd-Armstrong Bridge.  I am pleased that progress continued to be made over the course of the winter months, in sometimes difficult weather conditions.

Some of the work that is currently ongoing and was recently completed includes:

·    Completion of the concrete deck (used for construction traffic only);
·    Barrier walls are complete to the extent that they can prior to the placement of the expansion joints;
·    All deck formwork has been removed;
·    All underground piping/duct-work on the road approaches is complete, including Hydro, storm sewer, lighting, Rogers and Bell;
·    Road approaches are being prepared for final paving in the spring/summer;
·    Installation of bridge lighting;
·    Ongoing shoreline restoration, railing installation, and sidewalk formwork.

During the spring and summer months the following work items will be completed:

·    Completion of the deck sidewalks;
·    Railing installation;
·    Completion of the road approaches (granular base, asphalt paving, curb, sidewalk, guiderail, waterproofing);
·    Final painting of some areas of the arch structure;
·    Completion of the barrier walls;
·    Commissioning of street lighting and traffic signals.

I have also been in contact with OC Transpo officials to ensure the coordination of transit services is ongoing as we prepare the opening of the bridge toward September service changes and day one opening.  The completion of the bridge will help provide major service improvements for residents on both sides of the bridge and open transit opportunities through new rapid transit links.

City engineers continue to work very closely with the contractor to ensure all opportunities to accelerate the work continue to be explored. 

I look forward to the completion of the Strandherd-Armstrong Bridge project.

The planned completion date for the bridge remains September 2014.

kbhc
 

bridge construction

 

fb
Follow Steve on Facebook
 

2017ottawa-weblink

alt

OCTranspo 485 Small

sab

ottawa small

Wardmap side

sab

 

Serving the Communities of Barrhaven, Riverside South and Findlay Creek

Login Form